A city is trying to estimate the most money it should offer to contractors as an incentive for them to finish a disruptive road project early. The transportation project lengthens transport times by 10 hours per week for 40,000 workers. Assume that all workers are paid $10 per hour in a perfectly competitive labor market. What is the most that the city should pay to the contractors as an incentive for completing the project four weeks early? HTML EditorKeyboard Shortcuts

User FraZer
by
4.6k points

2 Answers

5 votes

Answer:

$16,000,000

Step-by-step explanation:

To answer this question we pull out information relevant to us as follows

What is the number of workers = 40,000workers

How many labour hours per week = 10 hours per week

What is the hourly wage = $10/hour

First, Amount spent per worker in a week =

$10 x 10 hours = $100 per week

Second, Amount to be expended for 4 weeks

= $100 x 4 weeks = $400

Finally, the most that should be paid to the contractor for workers

$400 x 40,000 workers

= $16,000,000

User JustABill
by
4.7k points
1 vote

Answer:

The city should pay at most $16 million to the contractors as an incentive for completing the project four weeks earlier.

Step-by-step explanation:

Total number of saved work hours = 4 weeks * 40000 workers/week * 10 hours/worker = 1,600,000 work hours

So, Money saved = 1,600,000 work hours * $10/ work-hour

= $16 million

Therefore, the city should pay at most $16 million to the contractors as an incentive for completing the project four weeks earlier.

User BobMcboberson
by
4.4k points