Answer:
$16,000,000
Step-by-step explanation:
To answer this question we pull out information relevant to us as follows
What is the number of workers = 40,000workers
How many labour hours per week = 10 hours per week
What is the hourly wage = $10/hour
First, Amount spent per worker in a week =
$10 x 10 hours = $100 per week
Second, Amount to be expended for 4 weeks
= $100 x 4 weeks = $400
Finally, the most that should be paid to the contractor for workers
$400 x 40,000 workers
= $16,000,000