Round Robin Algorithm

Using the following table as your starting point for each algorithm RR with a time quantum of 5

Job
A
B
C
D
E

Arrival time:
0
0
0
0
0

Time burst:
15
2
14
10
1

1 Answer

5 votes

Answer:

Please check the attachment.

Step-by-step explanation:

avg turnaround time = (38+7+42+33+18)/5= 27.6

avg waiting timee = (33+5+28+23+17)/5= 21.2

And its D, A C in Gantt chart at last and exit time are 33, 38 and 42 mentioned as last three in Gantt chart.

Round Robin Algorithm Using the following table as your starting point for each algorithm-example-1