Answer:
Please check the attachment.
Step-by-step explanation:
avg turnaround time = (38+7+42+33+18)/5= 27.6
avg waiting timee = (33+5+28+23+17)/5= 21.2
And its D, A C in Gantt chart at last and exit time are 33, 38 and 42 mentioned as last three in Gantt chart.