Answer:
Instructions are listed below.
Step-by-step explanation:
Giving the following information:
Assume that the Assembly Department allocates overhead using a plantwide overhead rate based on machine hours.
The first thing that we need is the predetermined overhead rate. We weren't provided with this information, but I will give the formula and a small example to guide an answer:
To calculate the estimated manufacturing overhead rate we need to use the following formula:
Estimated manufacturing overhead rate= total estimated overhead costs for the period/ total amount of allocation base
For example:
Estimated overhead= $200,000
Estimated machine hours= 35,000
Estimated manufacturing overhead rate= 200,000/35,000= $5.71 per machine hour
Now, we can allocate overhead:
Allocated MOH= Estimated manufacturing overhead rate* Actual amount of allocation base
Because it is a plantwide overhead rate, we need to sum the total machine hours required:
Machine hours= 2.5 + 0.5= 3 machine hours
Allocated MOH= 5.71*3= $17.13 per unit