Answer:
The FIRST STEP of the procure-to-pay cycle is ordering;
Step-by-step explanation:
The procure to pay cycle is the set of activities required to follow through a buying process in a company, it includes identifying the need, looking for and assigning a vendor, approving the vendor's specifications, receiving the supplies and finally paying the money owed to the vendor. This process consists of five steps:
- ordering
- follow up and expediting
- receipt and inspection
- settlement and payment
- records maintenance