166k views
2 votes
The __________ of the procure-to-pay cycle is ordering; the most common way the ordering step begins is through the release of a purchase order. A purchase order (PO) is simply a document that authorizes a supplier to deliver a product or service and often includes terms and conditions, such as price, delivery, and quality requirements.

User Levand
by
5.8k points

1 Answer

3 votes

Answer:

The FIRST STEP of the procure-to-pay cycle is ordering;

Step-by-step explanation:

The procure to pay cycle is the set of activities required to follow through a buying process in a company, it includes identifying the need, looking for and assigning a vendor, approving the vendor's specifications, receiving the supplies and finally paying the money owed to the vendor. This process consists of five steps:

  1. ordering
  2. follow up and expediting
  3. receipt and inspection
  4. settlement and payment
  5. records maintenance

User Dove
by
6.6k points