156k views
4 votes
In an activity-based costing system, what should be used to assign a department’s manufacturing overhead costs to products produced in varying lot sizes?

User Ed Mendez
by
8.0k points

1 Answer

4 votes

Answer: Multiple cause-and- effect relationship should be used

Step-by-step explanation:

A multiple cause-effect relationship is a relationship in which an event (the cause) makes another event happen (the effect).

A particular cause can have several effects.

User Kanishk Dudeja
by
7.8k points
Welcome to QAmmunity.org, where you can ask questions and receive answers from other members of our community.

9.4m questions

12.2m answers

Categories