Camden Corporations agreed to build a warehouse for a client at an agreed contract price of $ 900,000. Expected (and actual) costs for the warehouse follow: 2016, $202,500; 2017, $337,500; and 2018, $135,000. The company completed the warehouse in 2018. Compute revenues, expenses, and income for each year 2016 through 2018, and for all three years combined, using the cost-to-cost method.

User KOssi
by
4.9k points

1 Answer

6 votes

Answer:

Key figures:

2016:

Revenue = $270,000

Expenses = $202,500

Income = $67,500

2017:

Revenue = $450,000

Expenses = $337,500

Income = $112,500

2018:

Revenue = $180,000

Expenses = $135,000

Income = $45,000

Step-by-step explanation:

Under this method, percentage of work completed is determined using the following formula:

Percentage of work completed = (Total Expenses incurred on the project till the close of the accounting period) ÷ (Total Estimated Cost of the Contract)

Total estimated cost = $202,500 + $337,500 + $135,000 = $675,000

2016:

Percentage of work completed = ($202,500 ÷ $675,000)×100 = 30%

Expenses in 2016 = $202,500 (answer)

Revenue in 2016 = $900,000 × 30% = $270,000 (answer)

Income in 2016 = Revenue - Expenses

Income in 2016 = $270,000 - $202,500

Income in 2016 = $67,500 (answer)

2017:

Percentage of work completed = ($337,500 ÷ $675,000)×100 = 50%

Expenses in 2017 = $337,500 (answer)

Revenue in 2017 = $900,000 × 50% = $450,000 (answer)

Income in 2017 = Revenue - Expenses

Income in 2017 = $450,000 - $337,500

Income in 2017 = $112,500 (answer)

2018:

Percentage of work completed = ($135,000 ÷ $675,000)×100 = 20%

Expenses in 2018 = $135,000 (answer)

Revenue in 2018 = $900,000 × 20% = $180,000 (answer)

Income in 2018 = Revenue - Expenses

Income in 2018 = $180,000 - $135,000

Income in 2018 = $45,000 (answer)