Answer:
210,000 units
Step-by-step explanation:
The computation of the total number of equivalent units for materials in July is given below:
= Completed and transferred out units + ending work in process units
= 165,000 units + 45,000 units
= 210,000 units
By adding the completed & transferred units and the ending work in process units we get the total number of equivalent units for material