Minor Company had the following department data: Physical Units Work in process, July 1 30000 Completed and transferred out 165000 Work in process, July 31 45000 All materials are added at the beginning of the process. What is the total number of equivalent units for materials in July

User Maxcnunes
by
5.0k points

1 Answer

6 votes

Answer:

210,000 units

Step-by-step explanation:

The computation of the total number of equivalent units for materials in July is given below:

= Completed and transferred out units + ending work in process units

= 165,000 units + 45,000 units

= 210,000 units

By adding the completed & transferred units and the ending work in process units we get the total number of equivalent units for material