Answer:
$2 per ball
Step-by-step explanation:
The computation of the fixed cost per ball is shown below:
Fixed cost per ball = Total fixed cost ÷ number of balls produced
where,
Total fixed cost = 15,000 balls × $3 = $45,000
And, the number of balls produced = 22,500 balls
So, the fixed cost per ball is
= $45,000 ÷ 22,500 balls
= $2 per ball
Hence, the fixed cost per ball is $2 per ball