Answer:
Step-by-step explanation:
Daily demand = 150 devices
Production rate per day = 300 devices
Ideal batch size = 900 devices
(a) Length of cycle in setup = batch size / production per day =900/300 =3 days.
(b) Avg inventory level = 1/2 x batch size ( 1- daily demand /daily production)
= 1/2*900* [ 1- 150/300] = 450*1/2 = 225
(c) Avg length of time spent by the a unit in inventory =
1/2 * ( Maximum time spent by a unit + minimum time spent in a unit)
= 0.5 * ( 6+0) = 3 days