Answer:
The number of units to be ordered is 961.
Explanation:
The optimum demand is given as

From the data
Daily demand is given as
=50
Standard deviation is given as

The Lead time is given as L=10 days
The Revier time is given as R=5 days
Initial values given as I=60 units
The confidence level is given as 99% so z is calculated using the NORMSINV() function as NORMSINV(0.99). The value of z is 2.33
Now the standard deviation in terms of the Lead and Review time is given as

Substituting the values in the formula as

So the number of units to be ordered is 961.