Answer:
=$57.754
Step-by-step explanation:
The question is to determine The Home Construction Company's Total Cost of Ordering and Carrying the nails as follows:
Known items
What is the demand or D= 4,765 boxes
What is the Fixed Ordering Cost = $0.70
The Carrying Cost = $0.5 per bag
Therefore the Equilibrum Order Quantity
= (2FD/C)∧1/2
= 2(0.70x 4,765) =
=6,671/0.5
= 13,342∧1/2
=115.507 or 116 boxes
Now the total Cost for Ordering and Carrying
= C(EOQ/2) + F(D/EOQ)
=$0.5 (58) + $0.70 (4,765/116)
= 29 + 28.754
=$57.754