Answer:
A. Project A = 0.9
Project B = 1
B. Project A should be chosen
C for project A, NPV = $12,934.05
For project B ,NPV = $14,194.03
D. Project B would be chosen
E. Net present value
Step-by-step explanation:
The payback period measures how long it takes to recover the amount invested in a project.
For project A, the pay back period = 18,000 / 20,000 = 0.9 year
For project B, the payback period is 18,000 / 18,000 = 1 year
Project A should he chosen because the payback period is shorter
The net present value is the present value of after tax cash flows from an investment less the amount invested.
The net present value can be calculated using a financial calculator:
For project A ,
Cash flow for year zero = -$18,000
Cash flow for year 1 = $20,000
Cash flow for year 2 = $8,000
Cash flow for year 3 = $7,000
Discount rate = 8%
NPV = $12,934.05
For project B,
Cash flow for year zero = -$18,000
Cash flow for year 1 = $18,000
Cash flow for year 2 = $7,000
Cash flow for year 3 = $12,000
Discount rate = 8%
NPV = $14,194.03
Project B should be chosen based on NPV because its NPV is greater than that of project A.
A firm should have more confidence in Npv because the NPV calculates using all cash flows while pay back period is only interested in the cash flows up until the amount invested in the project is recovered.
I hope my answer helps you