____ is a structured approach for organizing all the project work and deliverables into logical groupings and subdividing them into more manageable components to help ensure that all the work and deliverables to complete the project are identified and included in the baseline project plan.

User Laffuste
by
4.3k points

1 Answer

2 votes

Answer: Creating a work breakdown structure

Explanation: Work Breakdown Structure (WBS) is a hierarchical outline (map) that identifies the products and work elements involved in a project.

It is best suited for design and build projects that have tangible outcomes rather than process-oriented projects.