Answer:
12 weeks
Step-by-step explanation:
The computation of the needs period is shown below":
= Number of weeks inventory counts once + number of order cycles takes + number of the week taken for arrive
= 4 weeks + 2 weeks + 6 weeks
= 12 weeks
We simply added the total number of weeks that is mentioned in the question so that the needs period could be computed