Total time for 1 load: 35 + 75 + 15 = 125 minutes
Total time for 5 loads: 125 x 5 = 625 minutes.
1 hour = 60 minutes, divide total minutes by 60 to get hours:
625/ 60 = 10.4166 hours
10 hours and 25 minutes