Answer:
$240
Step-by-step explanation:
The computation of the overhead would be allocated to Job #804 for the quality control activity is shown below:
= Estimated overhead cost of Quality control ÷ Estimated amount of allocation base
= $320,000 ÷ $4,000 test runs
= $80
Now there are 3 quality control test runs
So, the allocated overhead is
= $80 × 3
= $240