154k views
5 votes
If a disruption occurs during work hours, then the BCP PM will probably be on the scene quickly. If the disruption occurs after hours, then the BCP PM should be contacted first thing the next business day.

a. True
b. False

1 Answer

5 votes

Answer:FALSE

Explanation:BCP(business continuity planning) is the term used to describe the overall steps and procedures employed by Organisations to prevent,handle and recover from potential threats to the general operations of the Business.

BCP plan ensures that both manpower and assets are protected and are able to effectively function quickly in the event of a disaster or threat.

BCP PM is not expected to be on the scene when the disruption occurs during work hours nor to be contacted first thing in the next business day.

User Tinesha
by
5.9k points