A(n) _____ is a formal, documented process that describes when and how official project documents may be modified, the people authorized to make modifications, and the paperwork required for these changes.

User Temeka
by
5.2k points

1 Answer

3 votes

Answer:

Change Control System

Step-by-step explanation:

The Change Control System is a collection of processes that allow change requests to be analysed, approved, declined, and then managed.

HOW IT WORKS

A change request enters the change control system. The change request is written, not verbal. The change request form follows a predetermined route as to how it’ll be analysed, either by the project manager, a change control board, or both.

When the change control board approves or declines the change request the change requester is informed of the project decision. All decisions on change requests are documented for future reference.