Answer:
Step-by-step explanation:
Under chase strategy , production is changed according to demand .
In the first quarter quantity demanded = 3000 units .
no of worker required
= 3000 / 135
= 22 ( approx )
So in the first quarter person to be hired
= 22-20 = 2
In quarter 2
quantity demanded = 500 units .
no of worker required
= 500 / 135
= 4 ( approx )
So in the second quarter person to be fired
= 22- 4 = 18