Shipments of Product X from a plant to a wholesaler are made in lots of 600. The wholesaler's average demand for X is 100 units per week. The lead time from the plant to the wholesaler is 4 weeks. The wholesaler pays for the shipments when they leave the plant.4. Refer to the scenario above. What is the total of the wholesaler's current cycle plus pipeline inventories

User Pitfall
by
6.9k points

1 Answer

7 votes

Answer: 1000 is the total wholesaler current cycle plus pipleline inventories.

Explanation: product X from a plant to a Wholesaler are made in lots of 600. Average demand of X is 100 units per week.

lead time from the plant is 4 weeks, So we have 100x4 =400