Answer: 1000 is the total wholesaler current cycle plus pipleline inventories.
Explanation: product X from a plant to a Wholesaler are made in lots of 600. Average demand of X is 100 units per week.
lead time from the plant is 4 weeks, So we have 100x4 =400
600+400=1000