Answer:
If direct labor hours: $ 17.6
If direct labor cost: $ 1.76
If machine hours: $ 8.8
Step-by-step explanation:
The company's overhead rate will be the quotient between the expect overhead cost and the choose cost driver.
If direct labor hours:
869,440 / 49,400 = 17.6
For every hour of labor 17.6 dollar of overhead are generated
If direct labor cost:
869,440 / 494,000 = 1.76
each dollar paid in wages also means there is 1.76 dollar of overhead cost
If machine hours
869,440 / 98,800 = 8.8
each hours the mahcines are on there is 8.80 dollar of overhead cost.