Answer:
d. $730.
Step-by-step explanation:
Material cost = $200
Direct labor expense = $15 x 10 = $150
Overheads = $38 x 10 = $380
Total cost $730
Predetermined overhead rate = Estimated total overhead / estimated direct labor hours = $760,000 / 20,000 = $38 per labor hour.