Answer:
Instructions are listed below.
Step-by-step explanation:
Giving the following information:
A company assigns overhead costs to completed jobs based on 115% of direct labor cost.
Job 413:
Direct materials= $23,085
Direct labor= $10,100
A total of 1,400 units were produced in Job 413.
A) To calculate the total cost of Job 413, we need to use the following formula:
Total cost= total direct material + total direct labor + total overhead
TC= 23,085 + 10,100 + (10,100*1.15)= $44,800
B) The unitary cost is calculated by the division of the total cost on the number of units:
Unitary cost= total cost/Q= 44,800/1,400= $32