Answer:
0, because the house is already painted. If this isn't a riddle then, it should take 4 days because that is half the people, two times the workload per person.
4 days
Explanation:
6 workers takes 2 days.
That means that each worker works 6*2 = 12 worker days.
To get the same amount it takes 3 workers 4 days to get 12 worker days.