Answer:
The cost amount of direct materials charged to Job 3318 is $19400 as shown below.
Step-by-step explanation:
In order to determine the amount of direct materials charged to Job 3318,the total costs of Job 3318 must for of all determined.The total costs is the sum of direct materials,direct labor costs and overhead consumed by Job 3318.
The formula below showing below ending month balance of work-in process represents the total costs incurred on Job 3318 as it is only left in process at month end:
Opening work-in-process+transfers in-Transfers out(finished goods=Ending work-in-process
=$13900+$81100+$54900+$41175-$160300=$30775
Hence total costs of Job 3318=$30775
Labor costs on the job is $6500
Overhead cost is 75% of labor costs=$6500*0.75=$4875
Direct material+direct labor +overhead=$30775
where direct material is unknown
$6500+$4875+direct material=$30775
Direct material =$30775-$11375
Direct material=$19400