While planning a new product launch, Cassandra knew that the art department was ready to work on the promotional pieces right away. But they are not able to start until the strategy group established the price point and the purchasing group obtained the paper needed to make the promotional piece. Establishing price points would take about a week and was dependent on manufacturing getting the costs to the strategy group. This was expected a week from today. The purchasing group indicated the paper could be obtained locally the same day it was requested. Based on this information and assuming things go according to plan, when will the art department be able to begin work on the promotional pieces?

User Mrksbnch
by
5.4k points

1 Answer

6 votes

Answer:

After 2 weeks.

Step-by-step explanation:

In this situation, the art department is fully dependent on Promotional Pieces because they have to work on it.

  • To buy Promotional pieces they need one week To maintain their cost and strategies to buy Promotional pieces.
  • After that, the Art Department needs to know about The selling price of the commodity to mention on Promotional paper but here strategy group department needs one week to Find manufacturing cost.

Therefore, the art department will begin after two weeks.