Spot Construction builds roads, bridges, and other infrastructure. The following is the budget for a road project along with the actual results (in thousands of dollars) for the last fifteen months. Budget Actual Month Cost %Complete Cost %Complete 0 $ 0 0.0 % $ 0 0.0 % 1 $ 510 5.0 % $ 700 5.5 % 2 $ 1,020 10.0 % $ 1,160 11.2 % 3 $ 1,530 15.0 % $ 1,820 13.4 % 4 $ 2,040 20.0 % $ 2,270 21.6 % 5 $ 2,550 25.0 % $ 2,810 27.5 % 6 $ 3,060 30.0 % $ 3,190 34.0 % 7 $ 3,570 35.0 % $ 3,870 36.5 % 8 $ 4,080 40.0 % $ 4,200 45.0 % 9 $ 4,590 45.0 % $ 4,710 48.8 % 10 $ 5,100 50.0 % $ 5,400 53.4 % 11 $ 5,610 55.0 % $ 5,920 56.7 % 12 $ 6,120 60.0 % $ 6,300 62.3 % At this time, what is the current cost over (under) run on the project?