Answer:
Job HE-65 total cost 900 dollars
Step-by-step explanation:
predeterminated overhead rate:
expected cost / expected driver
900,000 / 30,000 = $30
Each labor hour generates $30 dollars of overhead according to our expectation
Now we solve for the cost of job HE-65
materials 300
labor 15 hours x $10 = 150
and overhead 15 hours x $30 each = 450
total cost 300 + 150 + 450 0 900