Traves Corporation incurred $69,000 of actual Manufacturing Overhead costs during October. During the same period, the Manufacturing Overhead applied to Work in Process was $68,000. The journal entry to record the application of Manufacturing Overhead to Work in Process would include a:

User Timr
by
4.4k points

1 Answer

4 votes

Answer:

Dr. Cr.

Work in progess 68,000

Manufacturing overhead 68,000

Step-by-step explanation:

The appliesmanufacturing overhead will be recorded to work in process account by debiting Work in process and crediting manufacturing overhead account. Now it will be added to the value of work in process and ultimately added to the value of finished goods which is Inventory value.