In the cycle of complete strategic planning, taking corrective action is a part of ________. A. implementation B. controlling C. planning D. organizing

User Stpk
by
7.4k points

1 Answer

1 vote

Answer:

The correct answer is letter "B": controlling.

Step-by-step explanation:

In strategic planning, controlling is the step in which the project is being carried out but monitoring is needed to track the progress of work. Controlling will allow the company to find out if it is ahead or behind the scheduled plan and if there are corrections to be made or simple adjustments.