Answer:

The number of hours required to complete the batch are 4.667 hr
Explanation:
Time for each cycle=
= Part handling time + Operation time
Time for each cycle=
=0.50+1.67
Time for each cycle=
=2.17 min
Since Scrap Rate is 5 %=0.05:
Starting quantity of batch is:


≅106 Parts
Batch Time can be calculated as:
*(Starting batch quantity)+Setup Time

The number of hours required to complete the batch are 4.667 hr