Answer:
The answer to your question is Nick finish his homework at 4:05 pm
Explanation:
Data
First our = 2:25 pm
+ 15 min ride home
+ 30 min bike ride
+ 55 min doing homework
Process
1.- Add 15 min to 2:25 hrs
2:25
+ 15
2:40 pm
2.- Add 30 min to the previous result
2:40
+ 30
3:10 pm
3.- Add 55 min to the previous result
3:10 pm
+ 55
4:05 pm