Answer:
The question is missing the below options:
a) a debit to Cost of Goods Sold for $432,000.
b) a debit to Finished-Goods Inventory for $86,000.
c) a credit to Work-in-Process Inventory for $432,000.
d) a credit to Work-in-Process Inventory for $86,000.
e) a credit to Finished-Goods Inventory for $432,000.
The correct option is C,a credit to Work-in-Process Inventory for $432,000.
Step-by-step explanation:
$432,000 would credited to Work-in-Process Inventory as that is the value of finished goods inventory in the period.The debit goes to the finished goods inventory as goods manufactured in the period.The $432000 is calculated thus:
Opening Work-in-Process $68000
Manufacturing costs $450000
Closing Work-in-Process ($86000)
Finished goods $432000