Answer:
d. $8,670
Step-by-step explanation:
expected overhead / expected driver = rate
273,000 / 70,000 = 3.9 fixed overhead
the cost of the job will be the sum of labor, material and overhead
Job 50:
materials 680
DL 7,000
overhead:
100 hours x (3.9 fixed + 6 variable) = 990
Total cost: 8.670