Answer:
Rough-cut Capacity Planning (RCCP).
Explanation:
Rough-cut Capacity Planning is defined as the transformation of the Master Production Schedule (MPS) into the essential resource requirements. The main aim of Rough-cut Capacity Planning is to balancing the in-hand assets with the current demands.
- The Rough-cut Capacity Planning is the technique that is used to check the feasibility of the Master Production Schedule i.e MPS
- Rough capacity preparation is a simple and simplistic technique with little secret values or inventories