The medium-range capacity planning technique used to check the feasibility of the Master Production Schedule (MPS) is called?

User JP Alioto
by
4.4k points

1 Answer

1 vote

Answer:

Rough-cut Capacity Planning (RCCP).

Explanation:

Rough-cut Capacity Planning is defined as the transformation of the Master Production Schedule (MPS) into the essential resource requirements. The main aim of Rough-cut Capacity Planning is to balancing the in-hand assets with the current demands.

  • The Rough-cut Capacity Planning is the technique that is used to check the feasibility of the Master Production Schedule i.e MPS
  • Rough capacity preparation is a simple and simplistic technique with little secret values or inventories