Final answer:
The activity rate for the Order Size activity cost pool under activity-based costing is $16.21 per machine hour, calculated by dividing the total estimated overhead cost ($183,147) by the total expected machine hours (11,300 MHs).
Step-by-step explanation:
To calculate the activity rate for the Order Size activity cost pool under activity-based costing (ABC), we need to divide the total estimated overhead cost by the total expected activity for that cost pool.
Given data:
Estimated Overhead Cost for Order Size = $183,147
Total Expected Activity (MHs) for Order Size = 11,300 MHs
The activity rate can be calculated as follows:
Activity Rate for Order Size = Estimated Overhead Cost / Total Expected Activity
Activity Rate for Order Size = $183,147 / 11,300 MHs
Activity Rate for Order Size = $16.21 per MH (rounded to two decimal places)