121k views
2 votes
The resource management module of an advanced planning and scheduling (APS) system ______.

(A) develops the requirement projections for the planning horizon
(B) defines and coordinates supply chain system resources and constraints
(C) is the computational engine of the supply chain planning system
(D) specifies the resource assignments and communicates them to the ERP system

1 Answer

3 votes

Answer:

The correct answer is letter "B": defines and coordinates supply chain system resources and constraints.

Step-by-step explanation:

Advanced Planning and Scheduling or APS is a method that allows companies to track the units of production along the manufacturing cycle. The resource management of the APS is a helpful tool to allocate the needed raw materials alongside the supply chain and helps determine what the limits of the organizations could be.

User Shani Goriwal
by
4.3k points