Answer:
2,967 units
Explanation:
The computation of the reorder point is presented below:
= Demand × lead time + safety stock
where,
Demand equal to
= Expected demand ÷ total number of weeks in a year ÷ number of days in a week
= 60,000 ÷ 52 weeks ÷ 7 days
= 164.835
So, the reorder point would be
= 164.835 × 18 days + 0
= 2,967 units
All other information that is mentioned is not relevant. Hence, ignored it