The critical path of a network is the A. shortest time path through the network. B. path with the most activities. C. longest time path through the network. D. path with the fewest activities.

User Jemima
by
3.5k points

1 Answer

2 votes

Answer: Option [C] : The longest time path through the network.

Step-by-step explanation:

The critical path of a network is the longest time path through the network.