In project time management, the main goal of _____ is to ensure that the project team has complete understanding of all the work they must do as part of the project scope so they can start scheduling the work.

User Blinky
by
3.4k points

1 Answer

4 votes

Answer:

In project management,the main goal of DEFINING ACTIVITIES is to ensure that the project team has complete understanding of all work they must do as part of the project scope so they start scheduling work

Step-by-step explanation:

Scheduling as mentioned is allocating specific task to individual with the right skill to different areas of the planned object such that the project is completed in a time fashion as well as with a professional touch.