Answer:
Beginning WIP= 122,000
Step-by-step explanation:
Giving the following information:
Cost of goods manufactured= $524,000
Ending work in process= $79,000
Raw materials used in the production of $89,000
Direct labor of $145,000
Manufacturing overhead of $247,000
To calculate the beginning work in process we need to use the cost of goods manufactured formula:
cost of goods manufactured= beginning WIP + direct materials + direct labor + allocated manufacturing overhead - Ending WIP
524,000= Beginning wip + 89,000 + 145,000 + 247,000 - 79,000
Beginning WIP= 122,000