If 15 workers can paint 18 houses in 24

days, how many days will 40 workers take
to paint 22 houses?

1 Answer

1 vote

Answer: 11

Explanation:

If 15 workers can paint 18 houses in 24 days, how many days will 40 workers take to paint 22 houses?

--------------

# of days are inversely related to # of workers and directly related

to # of houses.

--------------

d = kh/w

---

Solve for "k" using "15 workers can paint 18 houses in 24 days"

24 = k*18/15

k = 15*24/18 = 15*(4/3) = 20

--------------

Equation:

d = 20h/w

---

Solve: How many days will 40 workers take to paint 22 houses?

d = 20*22/40

d = 11 days