Answer:
Estimated manufacturing overhead rate= $2.75 per machine hour
Step-by-step explanation:
Giving the following information:
Overhead costs are estimated to total $348,425 for the year, and machine usage is estimated at 126,700 hours.
To calculate the estimated manufacturing overhead rate we need to use the following formula:
Estimated manufacturing overhead rate= total estimated overhead costs for the period/ total amount of allocation base
Estimated manufacturing overhead rate= 348,425/126,700= $2.75 per machine hour