Answer:
Delayed, accelerated
Step-by-step explanation:
Total or aggregate slack, is the term which is defined for the activity, is the time that this activity could delayed without impacting on the final date of the project.
It can be computed as the:
Smaller value of Late finish - Early finish field
and
Late start - Early start field
So, when project has positive total slack, few activities delayed the completion of project and when the project has negative total slack, then few activities accelerated to finish the project.