Answer:
Step-by-step explanation:
What is given:
Currently bakery makes 1500 loaves per month (output)
Labor productivity = 2.344
Demand has increased by 25% in the last year
Work hours = 160 hours per month
Labor productivity = Output/Labor hours
2.344 = 1500/ labor hours
Labor hours = 639.93
Number of workers required to produce 1500 loaves equals to 639.93/160 = 3.999
Demand has increased by 25%:
Total output = (1500*0.25) + 1500 = 375 + 1500 = 1875 (amount neede to meet the demand)
Number of labor hours needed to meet the demand = 1875/2.344=799.92hours
Workers required to meet the demand = 799.92/160 = 5
So, lackey needs to add 1 more employee (5-3.999)