At the beginning of 2019, Florida Road Construction entered into a contract to build a road for the government. Construction will take 4 years. The following information as of 31 December 2009 is available for the contract:

1. Total revenue according to contract $10,000,000
2. Total expected cost $8,000,000
3. Cost incurred during 2009 $1,200,000
Assume that the company estimates percentage complete based on costs incurred as a percentage of total estimated costs. Under the completed contract method, how much revenue will be reported in 2009?
A. None.
B. $300,000.
C. $1,500,000.

User Billcyz
by
7.3k points

1 Answer

5 votes

Answer:

A. None

Step-by-step explanation:

A is correct because Under the completed contract method, no revenue would be reported until the project is completed.

User Yuriy Faktorovich
by
8.2k points

No related questions found

Welcome to QAmmunity.org, where you can ask questions and receive answers from other members of our community.

9.4m questions

12.2m answers

Categories