Activity sequencing involves reviewing the activity list and attributes, project scope statement, and milestone list to determine the relationships or dependencies between activities.a. Trueb. False

1 Answer

5 votes

Answer:

The correct answer is letter "A": True.

Step-by-step explanation:

Activity sequencing is the set of steps organizations follow to accomplish certain tasks or even to reach greater goals at the corporate level. The activity implies finishing with a stage and jumping into the next one immediately after that according to a line-up strategically outlined.