You have been assigned as the project manager for a new project that involves deployment of a new software application to all your organization's users. You're trying to acquire your project team. In which of the following forms of project organization would you be more likely to have greater control over your project resources

User Karthiga
by
4.7k points

2 Answers

1 vote

Answer:

Projectized Organizational Structure

Step-by-step explanation:

Projectized Organizational Structure

In projectized organizations, all activities are coordinated through the projects.

Project managers have complete authority over resources. All team members report to them. Project managers have enough authority they need to complete the project and they can accept the responsibility and its outcome.

Project managers have full authority over project resources. They control the budget and work assignments.Project managers have full-time team members under their control and can acquire based on what is needed. Team members are often collocated for better performance until the project ends.When the project is completed, the team i and resources are released.

User Nonos
by
4.1k points
6 votes

Answer:

Project oriented.

Step-by-step explanation:

In this structure,project managers usually have great deal of independence and authority which gives them the power to draw and use resources with little approval.