Answer:
25 kanban containers
Step-by-step explanation:
Given that,
Daily demand = 2,000 units
Production lead time = 4 days
Container size = 400 units
Lead time demand:
= Daily demand × Production lead time
= 2,000 units × 4 days
= 8,000 units
Safety Stock:
= Number of days × Daily demand
= 1 day × 2,000 units per day
= 2,000 units
Number of Kanban containers needed:
= (Lead time demand + Safety Stock) ÷ Container size
= (8,000 + 2,000) ÷ 400
= 10,000 ÷ 400
= 25