A team's attempt to list, on individual sticky notes, all of the possible threats and opportunities that could occur to an upcoming project might be used during the _____________ process.

User Len
by
4.3k points

1 Answer

4 votes

Answer:

The correct answer is letter "A": plan risk responses.

Step-by-step explanation:

Plan risk responses refer to the process in which a team is facing a problematic situation and to reduce threats reacts immediately identifying the opportunities available they have that could lead to a solution. To achieve that, risk management and register will be necessary.